Hyperscaler capex is still outrunning revenue: up 93% against 19%

Five companies' data-centre spending has become the largest single source of demand for chips and power; the question is how long it keeps rising faster than their own revenue.Is hyperscaler capex still the thing to watch, and when does its lift to earnings end?

Said 17 Nov 2026Data to Jul 2026 (filings) · chip output to Sep 2026 · updated 17 Nov 2026
Hyperscaler capex, four quarters$691bnto Q3 2026 · 357bn a year earlier
Capex growth, four quarters+93.5%to Q3 2026 · revenue +19.1%
Capex growth less revenue growth+74.4ppto Q3 2026 · four quarters each
Semiconductor output, y/y+19.9%Sep 2026 · rising for 86 months

Capex is still outrunning the companies' revenue

Is hyperscaler capex still the thing to watch, and when does its lift to earnings end?
  • The five companies spent $691bn on capex in the four quarters to Q3 2026, +93% on a year earlier.→ Exhibit 1
  • Capex grew 74 points faster than revenue over the four quarters to Q3 2026.→ Exhibit
  • Semiconductor output was +19.9% on a year earlier in September 2026.→ Exhibit
What would change this view
What would change this viewTriggerTodayDecided by
The spending stops growingthe five companies' capex over four quarters below a year earlier93.5% (Jul 2026)not crossed–
Spending falls behind revenuecapex growth below revenue growth, four quarters each74.4pp (Jul 2026)not crossed–
The chip cycle turnssemiconductor output below a year earlier19.9% (Sep 2026)not crossed–
The reasoning behind each point
  • Level
    The five companies spent $691bn on capex in the four quarters to Q3 2026, +93% on a year earlier.

    A year earlier the four-quarter total was $357bn. In Q3 2026 alone Amazon spent the most, $77.3bn (34% of the five).

  • Against revenue
    Capex grew 74 points faster than revenue over the four quarters to Q3 2026.

    Four-quarter revenue rose +19.1% and capex +93.5%. The test of the view is capex growth falling below revenue growth.

  • Chips
    Semiconductor output was +19.9% on a year earlier in September 2026.

    It has been above a year earlier for 86 months. Since 1990 it has fallen below a year earlier 5 times, for 1 to 11 months.

Next: Industrial production — output across all industries

Source: SEC EDGAR XBRL filings; Federal Reserve G.17 · data to the dates shownthemes.ai_capex-read

The claim as written

The author's claim on 17 Nov 2026, kept as written; a figure revised since is marked where it stands
As written on 17 Nov 2026

Hyperscaler capex is still the thing to watch: while it grows faster than the companies' own revenue it carries chip demand, and its lift ends when it stops growing.

The canvas's board S10 reads the five companies' capex as the driver of tech and semiconductor earnings and asks when the lift ends. This page tracks the spending in the companies' own filings — the level, its growth against revenue — and the chip cycle in the Federal Reserve's output data. It does not yet print the earnings effect of a pause: that needs the sector engine.

StatusactiveSaid17 Nov 2026

Argued in the : 2 dated documents, listed with their sections under Sources in the Appendix.

Source: the September 2026 report and its research notes (2 documents, listed in the Appendix)themes.ai_capex-1

Capex rose 93% over four quarters, revenue rose 19%

How much are the five companies spending, and is it growing faster than what they earn?

Exhibit 1 · The five companies spent $691bn on capex in the four quarters to Q3 2026, +93% on a year earlier.

$ billions, sum of the four quarters to each date, Q3 2018 to Q3 2026; capex and revenue as each company files them
About this exhibit
Capex and revenue of five hyperscalers, four-quarter sums
Source: Source: U.S. Securities and Exchange Commission (EDGAR XBRL financial data); four-quarter sums calculated on this site (data to Jul 2026)themes.ai_capex-2

Capex grew 74 points faster than revenue over the four quarters to Q3 2026.

% change on a year earlier, four-quarter sums; the gap is capex growth less revenue growth, in percentage points
About this exhibit
Capex growth and revenue growth of five hyperscalers
Source: Source: U.S. Securities and Exchange Commission (EDGAR XBRL financial data); four-quarter sums calculated on this site (data to Jul 2026)themes.ai_capex-3

Capex by company, Q3 2026

$ billions in the quarter, change on the same quarter a year earlier, and share of the five
CompanyQuarterA year earliery/yShare
Microsoft39.419.4+103%17%
Amazon77.335.1+120%34%
Alphabet51.424.0+114%22%
Meta Platforms33.918.8+80%15%
Oracle28.58.5+235%12%
Source: Source: U.S. Securities and Exchange Commission (EDGAR XBRL financial data); four-quarter sums calculated on this site (data to Jul 2026)themes.ai_capex-5

Quarterly capex of each of the five hyperscalers

$ billions in each calendar quarter, Q3 2018 to Q3 2026
Source: Source: U.S. Securities and Exchange Commission (EDGAR XBRL financial data); four-quarter sums calculated on this site (data to Jul 2026)themes.ai_capex-6

The chip cycle the spending feeds

Is semiconductor output still rising, and how long have its downturns lasted?

Semiconductor output was +19.9% on a year earlier in September 2026

% change on twelve months earlier, G.17 semiconductors and related electronic components, monthly, to Sep 2026
About this exhibit
Semiconductor output, change on a year earlier
Source: Source: Board of Governors of the Federal Reserve System (G.17) (IP.G3344.S); % on a year earlier calculated on this site (data to Sep 2026)themes.ai_capex-4

Runs of semiconductor output growth below zero

Each stretch of months in which output was below its level a year earlier, and the current run
FromToMonths
Nov 2001Dec 20012
Nov 2008Sep 200911
May 2015Nov 20157
Jan 2016Jan 20161
Nov 2018Jul 20199
Aug 2019Sep 2026 (current, rising)86
Source: Source: Board of Governors of the Federal Reserve System (G.17) (IP.G3344.S); % on a year earlier calculated on this site (data to Sep 2026)themes.ai_capex-7

3 tests of the view, none crossed

What would change the view?

What would change the view, test by test

Thresholds from the September report; status from the latest data. 0 crossed · 0 closing · 3 not crossed · 0 pending · 0 not tracked here.
About
StatusTestLatest readingThresholdIf crossedThreshold source
not crossedThe five companies' capex over four quarters falls below a year earlier93.5% (Jul 2026)an earlier page of this site< 0.0%The spending has stopped growing; the canvas's pause path is the one under way.Proposal: integrating the earnings-stretch valuation work into the site (rev 42) · Page designs — AI capex: would change the view · 17 Nov 2026
not crossedCapex growth falls below revenue growth, four quarters each74.4pp (Jul 2026)an earlier page of this site< 0.0 ppSpending no longer runs ahead of the companies' own revenue: the spending is being paced by what the companies earn.Proposal: integrating the earnings-stretch valuation work into the site (rev 42) · Page designs — AI capex: open charts (capex growth less revenue growth) · 17 Nov 2026
not crossedSemiconductor output falls below a year earlier19.9% (Sep 2026)an earlier page of this site< 0.0%The chip cycle has turned with or ahead of the spending.Proposal: integrating the earnings-stretch valuation work into the site (rev 42) · Page designs — AI capex: folded (the pause runs) · 17 Nov 2026
Source: the September 2026 report (thresholds); the pages named in each row (readings)themes.ai_capex-8

The paths the canvas named, without odds

What does the spending do next?

What the spending does next

The two paths the canvas's board S10 names
About
  1. The spending keeps risingCapex keeps growing faster than revenue, chip output keeps rising, and the lift to tech and semiconductor earnings runs on.
  2. A capex pauseCapex growth falls below zero over four quarters, chip output follows it down, and the earnings lift reverses — the canvas's pause run.

The canvas simulates the paths but its odds have no record yet (D-2026-11-17-OR13; the proposal's change 6), so none are shown.

Source: Proposal: integrating the earnings-stretch valuation work into the site (rev 42) · Page designs — AI capex; Model changes 6 · 17 Nov 2026themes.ai_capex-scenario-buildout

What would each path move?

None of this theme's branches is on the Scenarios set; no model on the site prices a capex path yet

What each path of the spending would move

Model-conditional: no branch of this page is projected on the Scenarios set, so no asset effect is printed for any of them.

Nothing is projected here. The spending keeps rising and A capex pause: the site's macro model carries no capex variable yet (D-2026-11-17-OR13).

The earnings effect of a capex pause on tech and semis needs the sector engine, which waits on a consensus source (D-2026-11-17-OR8).

What each path would do to core PCE, unemployment and real GDP is read on Thematic impact, under Outlook.

Source: the Scenarios and Transmission pages; Macro Review calculations · data to 16 Nov 2026 and Oct 2026themes.ai_capex-9

Consensus capex as quoted, with date and source

Quoted only: consensus estimates are not an input to any figure on this page
WhatAs quotedSource
Capex against cash flowsubscription dataReuters analysis of LSEG consensus estimates (22 Jul 2026): Microsoft, Alphabet, Amazon, Meta Platforms and Oracle are expected to raise annual capex by about $534 billion between 2025 and 2027, against about $340 billion more operating cash flow.Reuters, P. Murugaboopathy and G. Dogra, 22 Jul 2026 · analysis of LSEG consensus estimates · 22 Jul 2026
Consensus revisionssubscription dataThe same analysis: current-year consensus capex for the five rose from about $485 billion in January to about $730 billion in July 2026.Reuters, P. Murugaboopathy and G. Dogra, 22 Jul 2026 · analysis of LSEG consensus estimates · 22 Jul 2026
Source: the September 2026 report's documents, quoted with dates; not a data feedthemes.ai_capex-10

Timeline

Dated events in the record

The dated events behind the view

Events with their source; scheduled dates are marked, and events read from a data series say so
  • 22 Jul 2026
    Reuters' analysis of LSEG consensus: the five companies' capex is expected to outrun their free cash flow by 2027.

    Reuters, P. Murugaboopathy and G. Dogra, 22 Jul 2026 · analysis of LSEG consensus estimates · 22 Jul 2026

  • 17 Nov 2026
    The theme opens on the site, reading the companies' filings through the third quarter of 2026.

    the site's specification for this page · 17 Nov 2026

Source: the September 2026 report and the pages cited per rowthemes.ai_capex-11

Method

Filings, sums, output data and licences27 checks, all pass
About this page

Five companies — Microsoft, Amazon, Alphabet, Meta Platforms and Oracle — report their capital spending and revenue to the SEC every quarter. This page adds them up, sets spending growth against revenue growth, and watches the chip cycle the spending feeds.

Definitions

  • Theme
    What the page reads.

    The theme reads the spending where it is recorded: each company's capital expenditure and revenue as filed with the SEC, read into calendar quarters the way the Fundamentals pages read every S&P 500 company, and semiconductor output from the Federal Reserve. Four-quarter sums remove the quarterly pattern and the companies' different fiscal years.

  • Capex
    The companies' own line.

    Capex is cash paid for property, plant and equipment as each company tags it (the tag read is named in the Data tab). Finance leases, which some companies report separately, are not added, so the totals are the companies' own capex line, not their full spending on data centres. A four-quarter sum is drawn only where all five companies report all four quarters.

  • Chips
    Output and its runs.

    Semiconductor output is the G.17 index for semiconductors and related electronic components (NAICS 3344), seasonally adjusted, as a percent change on twelve months earlier; a run is the stretch of months on one side of zero.

  • Consensus
    Quoted, never used.

    Consensus capex is quoted from the record with its date and source and is never an input: the site has no cleared source for consensus estimates (D-2026-11-17-OR8).

  • Status
    How triggers are scored.

    crossed — the threshold condition holds on the latest observation (for a run, on each of the last n); closing — not crossed, the series has printed since the September report's data date (11 September 2026), and the gap to the threshold is half or less of the gap on that date; not crossed — otherwise; pending — the observable is dated in the future or no page of this site carries it yet; not tracked here — an event, or subscription data this site does not display. Colours flag attention, not good or bad news for the book.

  • Odds
    None given.

    No odds are given for this theme. The two paths are named without a number.

  • Documents
    Where the view was argued.
    • the site's specification for this page · 17 Nov 2026
    • Proposal: integrating the earnings-stretch valuation work into the site (rev 42) · Page designs — AI capex (theme) · 17 Nov 2026
  • Licences
    What is quoted only.

    The filings and the output data are published. The Reuters figures are quoted only.

Source: Macro Reviewthemes.ai_capex-12

Before you read

Macro Review is a personal research site, still being built.

Nothing on it is investment advice, a recommendation or a solicitation.

Check every figure for yourself. Each names its publisher — confirm it there before you rely on it.

Figures can be revised, delayed or wrong.

Cones, fans, scenarios, fair values and “what followed” tables are conditional on the model each page names: they describe, they do not predict.