Completions have fallen to 1.19 million a year, the fewest since 2026
Is the housing pipeline growing or shrinking?
In brief
Is the building pipeline growing or shrinking?- Housing starts averaged 1.29 million a year over the last three months, down 4.1% on a year earlier.→ Exhibit 1
- Completions averaged 1.21 million a year over the last three months, down 17.1% on a year earlier.→ Exhibit 1
- The pipeline holds 24.6 months of completions at the current pace, against 21.3 in 2015–19.→ Exhibit 4
- Single-family permits (873k) are running below single-family starts (878k) on three-month averages.→ Exhibit 1
| What would change this view | Trigger | Today | Decided by |
|---|---|---|---|
| Multifamily starts fall back below completions | 5-or-more starts < 5-or-more completions, three-month averages, three months running | starts 403k vs completions 330k (Sep 2026)not crossed | the Oct 2026 new residential construction release (Census) |
| The 5-or-more pipeline normalises | 5-or-more pipeline < 22.9 months of completions (halfway to its ) | 24.6 months (Sep 2026)not crossed | the Oct 2026 new residential construction release (Census) |
The reasoning behind each point
- StartsHousing starts averaged 1.29 million a year over the last three months, down 4.1% on a year earlier.
In Sep 2026 alone starts ran at 1.22 million a year, down 7.4% on the year; the month's dip is inside the survey's error band. Single-family starts −4.6% to 859k; 5-or-more −7.2% to 349k. Over the last twelve months (unadjusted) starts are −1.9% on the prior twelve: 1 unit −3.5pp, 5 or more +1.9pp; by region the West moved most (−1.5pp).
- CompletionsCompletions averaged 1.21 million a year over the last three months, down 17.1% on a year earlier.
In Sep 2026 alone completions ran at 1.19 million a year, down 14% on the year, the lowest rate since Aug 2026. Single-family 840k (−11.0% y/y), 5 or more 339k (−20.4% y/y). Units under construction 1,280k, −3.3% y/y (90% CI ±2.7%). Starts less completions (three-month averages) is +79k at an annual rate: starts are running above completions, so the stock under construction has stopped shrinking.
- MultifamilyThe multifamily pipeline holds 24.6 months of completions at the current pace, against 21.3 in 2015–19.
Multifamily means buildings of five or more units (5+). 677k units under construction ÷ completions of 330k a year (three-month average). Multifamily starts are running at 403k, above completions by 73k a year, so the stock under construction is refilling. Permits authorized but not started: 123k (+13.9% y/y).
- PermitsSingle-family permits (873k) are running below single-family starts (878k) on three-month averages.
Permits lead starts by about a month for single-family homes (Census: 1.4 months from authorization to start in 2025). Total permits 1,400k, −0.2% m/m and −3.0% y/y; authorized but not started 279k (+9.8% y/y), 2.6 months of starts.
Next: New-home supply — the stock it feeds
Permits, starts and completions against the survey's own error
Permits, starts and completions at an — and is the change bigger than the survey's own error?Exhibit 1 · Three-month averages of new-home permits, starts and completions
About this exhibit
Exhibit 2 · Homes under construction and authorized but not started, by structure type
About this exhibit
Exhibit 3 · The selected stage by structure and region, with survey error bands
| Series | Level | From Aug 2026 | From Sep 2025 | Unadjusted, month | YTD 2026 | YTD 2025 | YTD change |
|---|---|---|---|---|---|---|---|
| Total | 1,221 | −5.2%±11.8 | −7.4%±11.5 | 103.8 | 1,036.5 | 1,048.0 | −1.1%±3.6 |
| 1 unit | 859 | −4.6%±10.0 | +2.6%±9.5 | 72.6 | 699.0 | 728.0 | −4.0%±3.2sig. |
| 5 units or more | 349 | −7.2%±27.7 | −25.9%±21.5sig. | 30.1 | 327.0 | 305.9 | +6.9%±10.9 |
| Northeast | 114 | ±0.0%±34.2 | −30.9%±32.1 | 9.9 | 109.2 | 100.9 | +8.3%±11.1 |
| Midwest | 158 | −19.0%±20.7 | −19.4%±21.0 | 14.4 | 150.4 | 153.5 | −2.0%±8.6 |
| South | 714 | +6.1%±15.5 | +11.0%±20.4 | 59.5 | 554.8 | 556.7 | −0.3%±4.4 |
| West | 235 | −23.2%±22.9sig. | −25.4%±14.3sig. | 19.9 | 222.2 | 237.0 | −6.3%±7.0 |
| Northeast, 1 unit | 49 | +4.3%±32.3 | −7.5%±26.6 | 4.3 | 40.5 | 47.4 | −14.7%±5.2sig. |
| Midwest, 1 unit | 120 | −13.7%±18.7 | +2.6%±22.0 | 11.1 | 97.3 | 101.2 | −3.9%±6.9 |
| South, 1 unit | 506 | −3.3%±12.4 | +8.8%±13.8 | 41.6 | 411.6 | 415.3 | −0.9%±4.3 |
| West, 1 unit | 184 | −3.7%±21.3 | −8.9%±20.0 | 15.5 | 149.6 | 164.0 | −8.7%±9.3 |
About this exhibit
Pipeline
Are units entering the pipeline faster than they leave it?Exhibit 4 · Construction pipeline in months: multifamily, single-family and authorized not started
About this exhibit
Exhibit 5 · Housing starts less completions: total and by structure type
About this exhibit
Stages, structures and regions
Which stage, which structure type and which region is moving?Exhibit 6 · Housing permits to completions by structure and region: levels and changes
| Series | Level | 3m avg | 1m | 3m | 1y | 3m avg y/y | Level pct since 2000 | 3m avg y/y, 36 months | As of |
|---|---|---|---|---|---|---|---|---|---|
| Building permits · SAAR | |||||||||
| Total | 1,400k | 1,412k | −0.2% | +1.9% | −3.0% | +1.1% | 49 | Sep 2026 | |
| 1 unit | 845k | 873k | −4.0% | −3.1% | −4.8% | −0.8% | 43 | Sep 2026 | |
| 2–4 units | 52k | 52k | +8.3% | −1.9% | −10.3% | −5.4% | 57 | Sep 2026 | |
| 5 units or more | 503k | 487k | +5.9% | +12.0% | +1.0% | +5.3% | 87 | Sep 2026 | |
| Northeast | 145k | 142k | +13.3% | −6.5% | −2.0% | +6.5% | 57 | Sep 2026 | |
| Midwest | 213k | 217k | +0.5% | +4.9% | +4.4% | +3.7% | 60 | Sep 2026 | |
| South | 759k | 752k | +1.5% | +7.2% | −1.8% | +0.5% | 59 | Sep 2026 | |
| West | 283k | 302k | −10.2% | −8.1% | −11.3% | −1.5% | 31 | Sep 2026 | |
| Authorized but not started · SA, end of month | |||||||||
| Total | 279k | 278k | +0.4% | +3.7% | +9.8% | +10.6% | 93 | Sep 2026 | |
| 1 unit | 151k | 150k | ±0.0% | +5.6% | +6.3% | +9.5% | 94 | Sep 2026 | |
| 5 units or more | 123k | 124k | ±0.0% | +0.8% | +13.9% | +11.4% | 89 | Sep 2026 | |
| Northeast | 23k | 23k | +4.5% | −14.8% | +21.1% | +25.5% | 72 | Sep 2026 | |
About this exhibit
Exhibit 7 · Construction pipeline in months and starts less completions, by structure type
| Series | Level | 3m change | 1y change | Pct since 2000 | Level, 10 years | As of |
|---|---|---|---|---|---|---|
| Pipeline ratios | ||||||
| Under construction ÷ completions, total | 12.7 | +1.7 | +1.8 | 91 | Sep 2026 | |
| Authorized not started ÷ starts, total | 2.6 | +0.2 | +0.3 | 99 | Sep 2026 | |
| Starts − completions, total (3m avg) | 79k | +109.7k | +195.0k | 59 | Sep 2026 | |
| Under construction ÷ completions, 1 unit | 8.1 | +0.3 | +0.9 | 89 | Sep 2026 | |
| Authorized not started ÷ starts, 1 unit | 2.1 | +0.2 | +0.1 | 100 | Sep 2026 | |
| Starts − completions, 1 unit (3m avg) | 6k | +13.7k | +119.3k | 42 | Sep 2026 | |
| Under construction ÷ completions, 5 units or more | 24.6 | +7.2 | +5.8 | 89 | Sep 2026 | |
| Authorized not started ÷ starts, 5 units or more | 3.7 | +0.3 | +0.7 | 87 | Sep 2026 | |
| Starts − completions, 5 units or more (3m avg) | 73k | +91.7k | +75.0k | 75 | Sep 2026 | |
About this exhibit
Exhibit 8 · Total housing starts: monthly and three-month average
About this exhibit
Where the change comes from
Single-family or ? Which region?Exhibit 10 · The selected stage's twelve-month change, split into its parts
About this exhibit
Exhibit 11 · The selected stage's growth by structure and region, last twelve months
| Series | Oct ’25 | Nov ’25 | Dec ’25 | Jan ’26 | Feb ’26 | Mar ’26 | Apr ’26 | May ’26 | Jun ’26 | Jul ’26 | Aug ’26 | Sep ’26 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | −5.8 | −2.9 | −4.7 | −1.6 | −5.3 | +1.5 | +1.1 | +2.1 | −0.8 | −2.7 | −0.2 | −4.1 |
| 1 unit | −14.0 | −12.0 | −8.5 | −9.8 | −12.3 | −6.6 | −4.4 | −0.6 | −4.2 | −5.8 | −2.9 | −1.3 |
| 5 units or more | +19.5 | +24.7 | +5.6 | +24.0 | +17.0 | +25.1 | +16.6 | +9.7 | +9.5 | +6.5 | +6.9 | −9.2 |
| Northeast | +2.8 | +15.3 | +14.7 | +28.6 | +21.1 | +29.4 | −1.9 | −1.2 | −16.3 | +16.5 | +20.1 | +18.5 |
| Midwest | −3.0 | −6.1 | −11.1 | −7.5 | +5.5 | +3.8 | +0.9 | −9.3 | +8.1 | +11.6 | +6.6 | −11.8 |
| South | −9.0 | −2.5 | −5.0 | −2.3 | −7.6 | +3.6 | +1.3 | +2.4 | −1.7 | −8.5 | −5.1 | −3.4 |
| West | −3.8 | −9.6 | −7.4 | −7.9 | −14.5 | −13.7 | +2.0 | +11.7 | +3.5 | −6.1 | −1.1 | −9.4 |
About this exhibit
Appendix
Surveys, adjustment, intervals, revisions and the model52 checks, all pass
Every new home passes through the same stages: a permit, a start, months under construction, a completion. Census counts each stage every month by structure type and region; this page follows the flow through the pipeline, separates signal from sampling noise with the published confidence intervals, and estimates when today's starts become tomorrow's supply.
Completions from past starts (Almon distributed lag)
| Symbol | Meaning | From | Assumed or estimated |
|---|---|---|---|
| completions, seasonally adjusted annual rate | Census, New Residential Construction | – | |
| starts k months earlier, seasonally adjusted annual rate | Census, New Residential Construction | – | |
| lag length, chosen by the Bayesian information criterion | – | – | |
| polynomial coefficients (degree 3) with Almon's endpoint restrictions | – | – | |
| mean lag in months | – | – |
Exhibit 12 · Definitions and caveats
- SurveysPermits are counted; starts are sampled.
Permits come from the Building Permits Survey of about 20,000 permit-issuing places (imputation for non-respondents was revised from the February 2025 release). Starts, units under construction and completions come from the Survey of Construction, a sample of permits followed through construction plus an area sample for places that issue no permits; they carry sampling error, which is why Census publishes 90% confidence intervals for their changes and none for permits.
- DefinitionsStart, completion, authorized.
A start is the beginning of excavation for the footings or foundation; all units in a multi-unit building are counted as started when the building is. A unit is completed when all finished flooring is installed, or at occupancy if that comes first. Authorized but not started counts units permitted in this or any earlier month on which construction had not begun at the end of the month.
- AdjustmentAnnual rates, regional adjustment, suppressed 2–4 units.
Seasonally adjusted flows are annual rates (unadjusted monthly × 12 ÷ seasonal factor); stocks are adjusted end-of-month levels. The adjusted U.S. total equals the sum of the four adjusted regions in every month (checked), so regions add exactly. Adjusted 2–4 unit starts, units under construction and completions are suppressed (Census: tests for identifiable and stable seasonality do not meet reliability standards); 1 unit and 5 or more therefore do not add to the adjusted total. Published factors reproduce the adjusted total, 1-unit and regional series of starts, under construction and completions within rounding (checked); permits and the 5-or-more series do not satisfy that identity in every month, consistent with being aggregated from separately adjusted components, and are left out of the check.
- Intervals90% confidence intervals.
A change is statistically significant when its 90% confidence interval excludes zero. In the Sep 2026 release the interval on the monthly change is ±11.8% for total starts and ±10.8% for total completions, so most monthly moves are not significant. Three-month averages and year-on-year changes of three-month averages are the steadier readings; the tables show both.
- RevisionsPreliminary, revised, annual.
The latest month is preliminary (p) and earlier months in the table may be revised (r); seasonal factors and recent history are also revised annually. Each update compares the release table with the historical workbook cell by cell (checked). Census: year-to-date permits estimates reflect revisions not reflected in the monthly data (release Table 1b note), so permit year-to-date totals differ from the sum of the monthly estimates; the check applies to starts and completions.
- ContributionsUnadjusted parts that add.
Contribution of a structure type or region to a stage's 12-month change: (x_i,t − x_i,t−12) ÷ X_t−12 × 100 on unadjusted data — 12-month sums for flows, end-of-month levels for stocks — so the parts add to the published total's change up to rounding (checked). 2–4 units are included unadjusted.
- ModelDistributed lag of completions on starts.
Almon distributed lag of completions on current and past starts, without intercept: weights follow a degree-3 polynomial with Almon's endpoint restrictions (zero weight one month before the first lag and one month after the last), so they rise and fall smoothly. The lag length is chosen by the Bayesian information criterion — 1 unit K = 16 months (grid 6–24), 5 or more K = 35 (grid 18–42) — fitted 1990–2019 on seasonally adjusted annual rates. Σβ is completions per start in the long run (below 1 where units are abandoned or reclassified); the mean lag is Σkβ_k ÷ Σβ_k. Projections hold starts after Sep 2026 at their three-month average; the 90% band is ±1.645 × the root-mean-square error of the same h-step procedure at every origin from 2020 (it includes the 2021–23 jump in construction times and ignores parameter uncertainty). Sensitivity to the polynomial degree, sample and lag length is shown beside the model.
- RecordHow the model has done.
Mean lags: single-family 6.3 months (Census's average start-to-completion time in 2025: 7.4); multifamily (5+ units) 13.9 months (Census, buildings with 2+ units: 16.5). Out of sample (2024 onwards) the single-family projection six months ahead has missed by 47k (root mean square) against 69k for carrying the latest completions forward; the 5-or-more projection twelve months ahead by 119k against 133k, with completions running 97k above the model on average — large buildings are taking longer than the 1990–2019 weights assume (fitted through Sep 2026 the mean lag is 18.4 months). The projection itself is drawn on the Housing supply theme page, which copies it from this page.
- Stock-flowWhy the stock does not equal starts less completions.
Units under construction should change by starts less completions. On unadjusted data the 12-month residual (change in the stock − starts + completions) has averaged -12k since 2000 (σ 16k; latest -36k): sampling error in three separately estimated series, abandoned projects and reclassified units. It is shown for context, not used as a check.
- NormsOwn history, 2015–19.
Shading compares each change with its own 2015–19 distribution (full colour at two standard deviations); percentiles run since 2000.
- LicenceFederal data only.
Private construction trackers (Dodge, CoStar, RealPage multifamily pipelines) and builder surveys (NAHB/Wells Fargo HMI) are paid data and are not used.
Sources
- publicU.S. Census Bureau and U.S. Department of Housing and Urban Development, New Residential Construction — August 2026 release workbook (newresconst.xlsx, Tables 1–5)
Source: U.S. Census Bureau and U.S. Department of Housing and Urban Development · https://www.census.gov/construction/nrc/xls/newresconst.xlsx
- publicU.S. Census Bureau and HUD, New Residential Construction historical time series: permits, authorized but not started, starts, under construction, completions (seasonally adjusted, not adjusted, seasonal factors)
Source: U.S. Census Bureau and U.S. Department of Housing and Urban Development · https://www.census.gov/construction/nrc/data/series.html
- publicU.S. Census Bureau and HUD, Average length of time from authorization to start and from start to completion (Survey of Construction)
Source: U.S. Census Bureau, Survey of Construction · https://www.census.gov/construction/nrc/data/time.html
Reproduction checks
| Check | Published | Computed | Tolerance | Result |
|---|---|---|---|---|
| Building permits: all 312 seasonally adjusted and unadjusted cells of the release table (Sep 2025–Sep 2026) equal the historical time-series workbook (cells that differ) | 0 | 0 | 0 | pass |
| Building permits, total: published change Sep 2026 from Aug 2026 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | -0.2 | -0.2138 | 0.1212 | pass |
| … every published month-on-month change in Table 1a (12 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Building permits, total: published change Sep 2026 from Sep 2025 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | -3 | -3.0471 | 0.1182 | pass |
| … every published year-on-year change in Table 1a (12 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Authorized but not started: all 299 seasonally adjusted and unadjusted cells of the release table (Sep 2025–Sep 2026) equal the historical time-series workbook (cells that differ) | 0 | 0 | 0 | pass |
| Authorized but not started, total: published change Sep 2026 from Aug 2026 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | 0.4 | 0.3597 | 0.411 | pass |
| … every published month-on-month change in Table 2a (11 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Authorized but not started, total: published change Sep 2026 from Sep 2025 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | 9.8 | 9.8425 | 0.4639 | pass |
| … every published year-on-year change in Table 2a (11 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Housing starts: all 299 seasonally adjusted and unadjusted cells of the release table (Sep 2025–Sep 2026) equal the historical time-series workbook (cells that differ) | 0 | 0 | 0 | pass |
| Housing starts, total: published change Sep 2026 from Aug 2026 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | -5.2 | -5.2019 | 0.1256 | pass |
| … every published month-on-month change in Table 3a (11 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Housing starts, total: published change Sep 2026 from Sep 2025 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | -7.4 | -7.4299 | 0.123 | pass |
| … every published year-on-year change in Table 3a (11 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Under construction: all 299 seasonally adjusted and unadjusted cells of the release table (Sep 2025–Sep 2026) equal the historical time-series workbook (cells that differ) | 0 | 0 | 0 | pass |
| Under construction, total: published change Sep 2026 from Aug 2026 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | 0 | 0 | 0.1282 | pass |
| … every published month-on-month change in Table 4a (11 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Under construction, total: published change Sep 2026 from Sep 2025 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | -3.3 | -3.2502 | 0.1244 | pass |
| … every published year-on-year change in Table 4a (11 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Completions: all 299 seasonally adjusted and unadjusted cells of the release table (Sep 2025–Sep 2026) equal the historical time-series workbook (cells that differ) | 0 | 0 | 0 | pass |
| Completions, total: published change Sep 2026 from Aug 2026 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | 2.2 | 2.2298 | 0.1368 | pass |
| … every published month-on-month change in Table 5a (11 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Completions, total: published change Sep 2026 from Sep 2025 reproduced from the rounded SA levels (%; tolerance = rounding of levels and of the published figure) | -14 | -13.9971 | 0.1171 | pass |
| … every published year-on-year change in Table 5a (11 cells by structure type and region) lies inside its rounding interval (cells outside) | 0 | 0 | 0 | pass |
| Housing starts: published 2026 year-to-date totals (Table 3b, total, types and regions) equal the sum of the 9 monthly unadjusted estimates within rounding (series outside ±0.50k) | 0 | 0 | 0 | pass |
| Completions: published 2026 year-to-date totals (Table 5b, total, types and regions) equal the sum of the 9 monthly unadjusted estimates within rounding (series outside ±0.50k) | 0 | 0 | 0 | pass |
| Building permits: published year-to-date percent changes (12 cells) reproduced from the published year-to-date totals within rounding (cells outside) | 0 | 0 | 0 | pass |
| Housing starts: published year-to-date percent changes (12 cells) reproduced from the published year-to-date totals within rounding (cells outside) | 0 | 0 | 0 | pass |
| Completions: published year-to-date percent changes (12 cells) reproduced from the published year-to-date totals within rounding (cells outside) | 0 | 0 | 0 | pass |
| Building permits: published annual totals 2024–2025 (24 cells) equal the sum of the twelve monthly unadjusted estimates within rounding (cells outside) | 0 | 0 | 0 | pass |
| Authorized but not started: published annual totals 2024–2025 (24 cells) equal the December unadjusted estimates within rounding (cells outside) | 0 | 0 | 0 | pass |
| Housing starts: published annual totals 2024–2025 (24 cells) equal the sum of the twelve monthly unadjusted estimates within rounding (cells outside) | 0 | 0 | 0 | pass |
| Under construction: published annual totals 2024–2025 (24 cells) equal the December unadjusted estimates within rounding (cells outside) | 0 | 0 | 0 | pass |
| Completions: published annual totals 2024–2025 (24 cells) equal the sum of the twelve monthly unadjusted estimates within rounding (cells outside) | 0 | 0 | 0 | pass |
| Building permits: four regions add to the U.S. seasonally adjusted total in every month Jan 2000–Sep 2026 (months off by more than 2k) | 0 | 0 | 0 | pass |
| … unadjusted: regions (321 months, ±0.25k) and 1 + 2–4 + 5-or-more units (321 months, ±0.2k) add to the total (months outside) | 0 | 0 | 0 | pass |
| Authorized but not started: four regions add to the U.S. seasonally adjusted total in every month Jan 2000–Sep 2026 (months off by more than 2k) | 0 | 0 | 0 | pass |
| … unadjusted: regions (321 months, ±0.25k) and 1 + 2–4 + 5-or-more units (321 months, ±0.2k) add to the total (months outside) | 0 | 0 | 0 | pass |
| Housing starts: four regions add to the U.S. seasonally adjusted total in every month Jan 2000–Sep 2026 (months off by more than 2k) | 0 | 0 | 0 | pass |
| … unadjusted: regions (321 months, ±0.25k) and 1 + 2–4 + 5-or-more units (321 months, ±0.2k) add to the total (months outside) | 0 | 0 | 0 | pass |
| Under construction: four regions add to the U.S. seasonally adjusted total in every month Jan 2000–Sep 2026 (months off by more than 2k) | 0 | 0 | 0 | pass |
| … unadjusted: regions (321 months, ±0.25k) and 1 + 2–4 + 5-or-more units (321 months, ±0.2k) add to the total (months outside) | 0 | 0 | 0 | pass |
| Completions: four regions add to the U.S. seasonally adjusted total in every month Jan 2000–Sep 2026 (months off by more than 2k) | 0 | 0 | 0 | pass |
| … unadjusted: regions (321 months, ±0.25k) and 1 + 2–4 + 5-or-more units (321 months, ±0.2k) add to the total (months outside) | 0 | 0 | 0 | pass |
| Building permits: 1 + 2–4 + 5-or-more units add to the seasonally adjusted total in every month since Jan 2000 (months off by more than 1.5k) | 0 | 0 | 0 | pass |
| Starts, under construction and completions (total, 1 unit, four regions and their 1-unit series): seasonally adjusted level = unadjusted × {12 for annual rates} ÷ published seasonal factor within rounding, 4230 monthly cells since 2015 (cells outside) | 0 | 0 | 0 | pass |
| Census distribution of units completed in 2025 by months from start to completion: each of 45 columns (U.S. and regions, by building type) sums to 100% within rounding (columns outside ±2.5) | 0 | 0 | 0 | pass |
| Contributions of structure types and of regions add to the published total's 12-month change, every stage, every month since Jan 2015 (max abs gap, pp; bound from unadjusted rounding) | 0 | 0.1641 | 0.7761 | pass |
| Every displayed seasonally adjusted series (total, 1 unit, 5 or more, four regions; five stages) is published in every month Jan 2000–Sep 2026 (missing months) | 0 | 0 | 0 | pass |
| Lag weights: each structure type's published shares of completions sum to 100% (max abs gap, pp) | 0 | 0 | 0 | pass |
| Decisions: every desk decision this page's specification names is in the decisions file (D-2026-10-03-10; ids missing) | 0 | 0 | 0 | pass |
- U.S. Census Bureau and U.S. Department of Housing and Urban Development, New Residential Construction — August 2026 release workbook (newresconst.xlsx, Tables 1–5) — Source: U.S. Census Bureau and U.S. Department of Housing and Urban Development
- U.S. Census Bureau and HUD, New Residential Construction historical time series: permits, authorized but not started, starts, under construction, completions (seasonally adjusted, not adjusted, seasonal factors) — Source: U.S. Census Bureau and U.S. Department of Housing and Urban Development
- U.S. Census Bureau and HUD, Average length of time from authorization to start and from start to completion (Survey of Construction) — Source: U.S. Census Bureau, Survey of Construction